Appendix B
Inquiry into Dunedin City Council and Otago Regional Council's funding of the proposed stadium.
MAIN STAGES OF THE STADIUM PROJECT
Based on information from the Trust’s June 2007 progress report
| Main stages of the project | Timeframes |
|---|---|
| Vision | June to August 2006 |
| Preliminary feasibility | July 2006 to June 2007 |
| Master Plan and Feasibility | September 2006 to March 2007 |
| Public funding and consultation | March 2007 to July 2008 |
| Private funding sources | July 2007 to December 2007 |
| Site acquisition | May 2007 to August 2008 |
| Plan change and resource consents | April 2007 to August 2008 |
| Design and construction (including concept design, developed design, construction procurement, construction) |
June 2007 to April 2011 |